Costa Mesa Sewer Rehab Along the I-405 Update

Home >> News >> Costa Mesa Sewer Rehab Along the I-405 Update

Current  Work: 

Upcoming work 7-22

LOCATION: Gisler Ave between College Ave and Gisler Park

  • What: Sewer line rehabilitation work
  • When:  Ongoing and lasting through October
  • Work Hours:  7:30 a.m.- 4 p.m., Monday-Friday (future updates to be provided regarding activities requiring continuous work hours)
  • Impacts: 
    •  Noticeable construction activity and construction equipment along Gisler Avenue and within Gisler Park
    • The Gisler Park walking trail/bike path along Fairview Road will be closed for approximately three weeks beginning September 16.
    • Increased noise due to construction activity
    • The contractor is currently preparing the site for rehabilitation of the pipelines. Read more about the rehabilitation work in the Upcoming Work section. More information will be provided as dates are finalized.

 

Upcoming Work

LOCATION: Gisler Ave between College Ave and Gisler Park

  • What:  Pipeline rehabilitation by lining the pipe using the cured-in-place-pipe (CIPP)  method. This work will occur in several segments.
  • When:  Anticipated to occur starting the week of September 23
  • Work Hours:  CIPP activities will require 24/7 continuous work
  • What to Expect:
    •  Some odors from the CIPP curing process may be noticeable in the immediate area but are temporary
    • Traffic control in work areas
    • Increase in activity and noise levels

LOCATION: Susan St and South Coast Dr (IKEA parking lot)

  • What: Sewer line rehabilitation work crossing under the 405 freeway
  • When: Anticipated to occur in September/October for approximately 2 nights
  • Work Hours: 9pm to 6am, night work
  • Impacts: This will work will occur in the parking lot area of IKEA during the nighttime hours and is anticipated to have minimal impacts to the public.

*All dates and times are subject to change due to operational factors or inclement weather.

Project Description:

This upcoming project will rehabilitate approximately 4 miles of the regional sewer pipeline that runs along the I-405 freeway in the City of Costa Mesa.

Project elements include the rehabilitation of gravity sewer pipelines using the cured-in-place pipe method, manhole structure rehabilitation, and manhole access improvements. The project also includes the rehabilitation of four sewer pipelines that cross the I-405 freeway.  (yellow line)

A nearby project also in the City of Costa Mesa is the Airway-Airport Loop Sewer Rehabilitation Project. (blue line)

 

 

Construction Schedule: 

Starting as early as summer 2024 and lasting approximately 1.5 years.

Work will be done in phases (segments) so as not to affect the entire project alignment at once.

Keep Informed:

Continue to follow this page as construction is anticipated to start on the project in the next several months.  Sign up for e-notifications to stay informed about this project by subscribing and selecting the “Costa Mesa Sewer Along the I-405” subscription topic.

Other Information: 

For information about nearby OC San construction work in the City of Costa Mesa, please visit Airway-Airport Loop Sewer Rehabilitation.